Can I put solar panels on my roof in Inner Sunset?
It takes a building permit. In the last 3 years, 33 permits for solar panels were filed in Inner Sunset and 22 issued, about 28 days from filing to issue.
Counted from the City of San Francisco's permit records, as of Nov 9, 2026.
Recent permits
In the last 3 years, 33 were filed and 22 issued. Typical time from filing to issue: about 28 days.
- 369 OAK PARK DR · Permit S20261019772
solar permit: installing 11 solar pv modules, 5 watts per module, total no. of rating 0.055 kw. mounted: roof, ballasted: n, including 1 energy storage unit, of 10 vac, with 10 kwh each in capacity, ess units will not be closer than 3 feet | rms: 11 mods, 5.06 kw/dc
filed · filed Oct 21, 2026 - 1884 16TH AV · Permit S20260910742
solar permit: installing 14 solar pv modules, 410 watts per module, total no. of rating 5.74 kw. mounted: roof, ballasted: yes, including 1 energy storage unit, of 240 vac, with 10 kwh in capacity | install roof mounted solar pv
filed · filed Sep 11, 2026 - 1833 11TH AV · Permit S20260908733
solar permit: installing 10 solar pv modules, 420 watts per module, total no. of rating 4.2 kw. mounted: roof, ballasted: n, including 1 energy storage unit, of 600 vac, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | 4.2kw pv array ( 10 pan
complete · filed Sep 8, 2026 · issued Sep 18, 2026 · 10 days - 369 OAK PARK DR · Permit S20260824722
solar permit: installing 11 solar pv modules, 5 watts per module, total no. of rating 0.055 kw. mounted: roof, ballasted: n, including 1 energy storage unit, of 10 vac, with 10 kwh each in capacity, ess units will not be closer than 3 feet | rms: 11 mods, 5.06 kw/dc,
issued · filed Aug 24, 2026 · issued Sep 25, 2026 · 32 days - 1350 06TH AV · Permit S20260729696
solar permit: installing 26 solar pv modules, 430 watts per module, total no. of rating 11.18 kw. mounted: roof, ballasted: n | install 11.18kw (26) roof mtd pv; (26) microinverters; (2) pw3 = total 27kwh; (2) tesla gw3; (2) rapid shutdown
filed · filed Jul 29, 2026 - 585 ORTEGA ST · Permit S20260709677
solar permit: installing 19 solar pv modules, 435 watts per module, total no. of rating 8.265 kw. mounted: roof, ballasted: n, including 2 energy storage unit, of 240 vac, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | 8.27 kw rooftop solar
issued · filed Jul 13, 2026 · issued Aug 28, 2026 · 45 days - 1543 07TH AV · Permit S20260529627
solar permit: installing 15 solar pv modules, 460 watts per module, total no. of rating 6.9 kw. mounted: roof, ballasted: n | new rooftop solar system 6.9 kw
filed · filed Jun 1, 2026 - 810 LAWTON ST · Permit S20260526622
solar permit: installing 24 solar pv modules, 420 watts per module, total no. of rating 10.08 kw. mounted: roof, ballasted: n, including 2 energy storage unit, of 600 vac, with 13.5 kwh each in capacity, ess units will be closer than 3 feet | revision changes s2025092
complete · filed May 26, 2026 · issued Jul 23, 2026 · 58 days - 1652 08TH AV · Permit S20260501586
solar permit: installing 18 solar pv modules, 440 watts per module, total no. of rating 7.92 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | installation of rooftop pv system
complete · filed May 1, 2026 · issued May 26, 2026 · 24 days - 1652 08TH AV · Permit S20260330528
solar permit: installing 18 solar pv modules, 440 watts per module, total no. of rating 7.92 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | installation of rooftop pv system
issued · filed Apr 1, 2026 · issued Apr 21, 2026 · 20 days
Other uses in Inner Sunset
- Can I open a café in Inner Sunset?
- Can I open a restaurant in Inner Sunset?
- Can I open a bar in Inner Sunset?
- Can I open a retail shop in Inner Sunset?
- Can I open an office in Inner Sunset?
- Can I build an ADU in Inner Sunset?
- Can I build a deck in Inner Sunset?
- Can I put up a business sign in Inner Sunset?
These counts cover the whole neighborhood. What your own project needs depends on its address and plans, so check your address before you start. City hall staff make every permit decision.