Can I put solar panels on my roof in Portola?
It takes a building permit. In the last 3 years, 17 permits for solar panels were filed in Portola and 14 issued, about 54 days from filing to issue.
Counted from the City of San Francisco's permit records, as of Nov 9, 2026.
Recent permits
In the last 3 years, 17 were filed and 14 issued. Typical time from filing to issue: about 54 days.
- 601 UNIVERSITY ST · Permit S20260810706
solar permit: installing 10 solar pv modules, 620 watts per module, total no. of rating 6.2 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 10.24 kwh each in capacity, ess units will not be closer than 3 feet | install residential roof mounted s
issued · filed Aug 10, 2026 · issued Sep 17, 2026 · 37 days - 520 CAMBRIDGE ST · Permit S20260727693
solar permit: installing 13 solar pv modules, 435 watts per module, total no. of rating 5.655 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 15 kwh each in capacity, ess units will not be closer than 3 feet | rooftop pv and bess in backyard
complete · filed Jul 28, 2026 · issued Sep 1, 2026 · 34 days - 695 BOWDOIN ST · Permit S20260612652
solar permit: mounted: roof, ballasted: n, including 1 energy storage unit, of 240 vac, with 5 kwh each in capacity, ess units will not be closer than 3 feet | addition of pw3 ess to exisitng solar
filed · filed Jun 12, 2026 - 601 UNIVERSITY ST · Permit S20260108427
solar permit: installing 10 solar pv modules, 620 watts per module, total no. of rating 6.2 kw. mounted: roof, ballasted: y, including 1 energy storage unit, of 51.2 vac, with 10.24 kwh each in capacity, ess units will not be closer than 3 feet | installation of a roo
cancelled · filed Jan 20, 2026 · issued Jun 30, 2026 · 161 days - 162 SWEENY ST · Permit S20251105294
solar permit: installing 10 solar pv modules, 405 watts per module, total no. of rating 4.05 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | solar roof mount,ext main service
issued · filed Jan 20, 2026 · issued May 19, 2026 · 119 days - 246 GIRARD ST · Permit S20251107303
solar permit: installing 8 solar pv modules, 430 watts per module, total no. of rating 3.44 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 10 kwh each in capacity, ess units will be closer than 3 feet | this is a revised plans for permit applic
complete · filed Nov 13, 2025 · issued Dec 11, 2025 · 28 days - 445 PRINCETON ST · Permit S20250925098
solar permit: installing 8 solar pv modules, 405 watts per module, total no. of rating 3.24 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | solar roof mount,3.24kw,8modules,1t
cancelled · filed Oct 24, 2025 · issued Dec 1, 2025 · 37 days - 880 COLBY ST · Permit S20251022246
solar permit: installing 9 solar pv modules, 405 watts per module, total no. of rating 3.645 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | roof mounted pv system, 9 modules
cancelled · filed Oct 24, 2025 · issued Mar 18, 2026 · 145 days - 384 HALE ST · Permit S20251010179
solar permit: installing 16 solar pv modules, 460 watts per module, total no. of rating 7.36 kw. mounted: roof, ballasted: n, including 1 energy storage unit, of 240 vac, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | solar roof mount 7.36k
filed · filed Oct 14, 2025 - 1027 BOWDOIN ST · Permit S20251006150
solar permit: installing 12 solar pv modules, 405 watts per module, total no. of rating 4.86 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | solar roof monut,4.86kw,12modules,
complete · filed Oct 8, 2025 · issued Nov 4, 2025 · 26 days
Other uses in Portola
These counts cover the whole neighborhood. What your own project needs depends on its address and plans, so check your address before you start. City hall staff make every permit decision.