Can I put solar panels on my roof in Inner Richmond?
It takes a building permit. In the last 3 years, 15 permits for solar panels were filed in Inner Richmond and 8 issued, about 16 days from filing to issue.
Counted from the City of San Francisco's permit records, as of Nov 9, 2026.
Recent permits
In the last 3 years, 15 were filed and 8 issued. Typical time from filing to issue: about 16 days.
- 145 10TH AV · Permit S20260928754
solar permit: installing 10 solar pv modules, 405 watts per module, total no. of rating 4.05 kw. mounted: roof, ballasted: n, including 1 energy storage unit, of 240 vac, with 13.5 kwh each in capacity, ess units will be closer than 3 feet | roof mounted pv 4.05kw and
filed · filed Sep 28, 2026 - 143 10TH AV · Permit S20260928753
solar permit: installing 15 solar pv modules, 405 watts per module, total no. of rating 6.075 kw. mounted: roof, ballasted: n, including 1 energy storage unit, of 240 vac, with 13.5 kwh each in capacity, ess units will be closer than 3 feet | roof mounted pv 6.07kw an
filed · filed Sep 28, 2026 - 167 11TH AV · Permit S20260610644
solar permit: installing 14 solar pv modules, 460 watts per module, total no. of rating 6.44 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | installation of a 6.44 kw dc gri
filed · filed Jul 13, 2026 - 431 LAKE ST · Permit S20260616655
solar permit: mounted: roof, ballasted: n, including 1 energy storage unit, of 240 vac, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | addition of ess to previously permited
issued · filed Jun 18, 2026 · issued Oct 19, 2026 · 122 days - 167 11TH AV · Permit S20260610643
solar permit: installing 14 solar pv modules, 460 watts per module, total no. of rating 6.44 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | installation of a 6.44 kw dc gri
filed · filed Jun 18, 2026 - 555 06TH AV · Permit S20260430583
solar permit: ballasted: n, including 1 energy storage unit, of 600 vac, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | 13.5kwh storage system ( 1 ess )
filed · filed May 1, 2026 - 4126 CALIFORNIA ST · Permit S20260310502
solar permit: installing 114 solar pv modules, 57 watts per module, total no. of rating 6.498 kw. mounted: roof, ballasted: n | installation of a 6.498 kw bipv solar shingle system. breaker tie-in. solar shingles are nailed to the roof and do not utilize rack.
issued · filed Mar 11, 2026 · issued May 7, 2026 · 57 days - 158 10TH AV · Permit S20251231421
solar permit: installing 14 solar pv modules, 410 watts per module, total no. of rating 5.74 kw. mounted: roof, ballasted: n, including 1 energy storage unit, of 240 vac, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | 5.74kw roof mt pv(14xq
complete · filed Jan 8, 2026 · issued Jan 22, 2026 · 14 days - 104 11TH AV · Permit S20251219403
solar permit: installing 16 solar pv modules, 440 watts per module, total no. of rating 7.04 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | installation of rooftop pv system
issued · filed Dec 22, 2025 · issued Jan 5, 2026 · 13 days - 710 05TH AV · Permit S20251212389
solar permit: ballasted: n, including 1 energy storage unit, of 240 vac, with 13.5 kwh each in capacity, ess units will not be closer than 3 feet | installation of tesla powerwall 3 with gateway and remote energy meter
complete · filed Dec 15, 2025 · issued Dec 29, 2025 · 14 days
Other uses in Inner Richmond
- Can I open a café in Inner Richmond?
- Can I open a restaurant in Inner Richmond?
- Can I open a bar in Inner Richmond?
- Can I open a retail shop in Inner Richmond?
- Can I open an office in Inner Richmond?
- Can I build an ADU in Inner Richmond?
- Can I build a deck in Inner Richmond?
- Can I put up a business sign in Inner Richmond?
These counts cover the whole neighborhood. What your own project needs depends on its address and plans, so check your address before you start. City hall staff make every permit decision.